How Long a Home Remodel Really Takes in Clark County, WA

Scheduling & Process · 6 min read

Almost every "behind schedule" remodel was never actually on a schedule. The work itself is predictable; the decisions, orders, and approvals around it are what move the finish date.

Typical durations, start to punch list

ProjectPre-constructionOn site
Bathroom remodel2–4 weeks3–5 weeks
Kitchen remodel4–8 weeks8–14 weeks
Flooring replacement1–3 weeks3 days–2 weeks
Siding & rot repair (section)1–2 weeks1–2 weeks
Water damage repairImmediate2–5 weeks after drying

Pre-construction is real work, not waiting. It's measurement, scope, selections, ordering, and permitting — and it's the part homeowners most often underestimate.

The five stages of a well-run job

  1. Scope and design. Measurements, drawings where needed, and a written scope you can actually price against.
  2. Selections and ordering. Everything long-lead — cabinets, tile, glass, specialty fixtures — ordered before demo starts.
  3. Permits. Filed once scope is fixed. Changing scope after submittal restarts review.
  4. Construction. Demo, rough trades, inspection, insulation and drywall, finishes, in that order.
  5. Punch and closeout. Walkthrough list, final inspection, cleanup, warranty documentation.

Rule of thumb: don't swing a hammer until the long-lead items are on order. Starting demo early feels like progress and usually just extends the number of weeks your kitchen is unusable.

What actually causes delays here

What you can do to keep it moving

Before you sign anything, run the checklist in our contractor vetting guide — a vague scope is the most common root cause of a schedule that slips.

Frequently asked questions

How long does a kitchen remodel take in Clark County?

Plan on eight to fourteen weeks on site for a full kitchen, plus four to eight weeks before that for design, selections, and cabinet ordering. Cabinets are usually the long pole — lead times commonly run six to twelve weeks.

How long do permits take in Clark County or Vancouver?

Simple over-the-counter trade permits can be same-day to a few days. Plan-review permits for structural or layout changes typically take a few weeks. Timelines vary by jurisdiction and workload, so your contractor should confirm current review times when scoping.

What causes most remodel delays?

Late selections by the homeowner, long-lead special orders, mid-project change orders, and unforeseen conditions found at demo — rot, old wiring, non-code framing. Inspections rarely delay a well-planned job; unmade decisions almost always do.

Can I live in the house during a remodel?

For a single bathroom or a contained room, usually yes. For a kitchen, expect several weeks without a sink or range and plan a temporary setup. Whole-floor work with dust containment is livable but disruptive.

Why does the last 5% take so long?

Punch list work depends on multiple trades returning for small items — a glass installer, a touch-up painter, one trim carpenter. Sequencing several short visits takes longer than the work itself. A good PM schedules them in one wave.

Keep reading

RestorationRepublic manages the schedule as tightly as the scope — one project manager, one written timeline, one accountable point of contact across SW Washington.

Talk to a real project manager

RestorationRepublic handles kitchens, baths, repairs, and water damage across SW Washington — one licensed contractor, one written scope, one accountable point of contact.

Request a Project Timeline